No products in the cart.
PMI-RMP Exam Questions
Page 5 of 25
81.
Mary, a Risk Analyst at GreenEarth Corp., identified a potential environmental risk that could impact the company's operations. She believes that this risk wasn't considered in the past. What should be Mary's next step?
-
Formally document the risk and present it to the risk management team for evaluation
-
Ignore the risk since it wasn't identified in previous assessments
-
Address the risk only if it becomes a significant issue in the future
-
Inform her colleagues about the risk during casual conversations
Correct answer: Formally document the risk and present it to the risk management team for evaluation
Risk management is an ongoing process that doesn't conclude. As the business environment evolves and new strategic opportunities arise, organizations must review their risks, identify new ones, and adapt to changing circumstances. This dynamic process may also necessitate building greater organizational capabilities.
Ignoring a newly identified risk can lead to unforeseen consequences.
Waiting for a risk to become significant before addressing it can result in missed mitigation opportunities.
Informal conversations are not an effective way to communicate and address risks.
82.
As the risk manager for your organization, you are working closely with a project manager on one of her critical projects. You use the assumptions and constraints analysis to assess potential impacts of various risks. Which of the following is also true about assumptions and constraints analysis?
-
Though initially accepted, these statements must be regularly validated and consistently reviewed throughout the iterative process and within the context of risk management for portfolio, program, and project life cycles
-
While initially embraced, these statements should be consistently disregarded and not subject to review during the iterative process and within the context of risk management for portfolio, program, and project life cycles
-
Although initially rejected, these statements must be perpetually challenged and never revisited throughout the iterative process and within the context of risk management for portfolio, program, and project life cycles
-
Despite initial acceptance, these statements should be sporadically acknowledged and rarely reconsidered during the iterative process and within the context of risk management for portfolio, program, and project life cycles
Correct answer: Though initially accepted, these statements must be regularly validated and consistently reviewed throughout the iterative process and within the context of risk management for portfolio, program, and project life cycles
Assumptions and constraints analysis involves using statements accepted as true to assess their potential impact on risk. Though initially accepted, these statements must be regularly validated and consistently reviewed throughout the iterative process and within the context of risk management for portfolio, program, and project life cycles. This technique comprises three essential steps: (1) listing the assumptions, (2) validating their accuracy, and (3) identifying their effects on the project, program, or portfolio.
Disregarding assumptions and constraints is not a sound risk management practice.
Perpetually challenging statements that are initially rejected is not the typical approach to managing assumptions and constraints.
Sporadically acknowledging and rarely reconsidering accepted statements does not align with the practice of regularly validating and reviewing assumptions and constraints.
83.
A project team is midway through the execution phase when they encounter a significant technological change in their industry, impacting their current project. How should the project manager address this new external risk?
-
Conduct a risk assessment to understand the impact and then update the project plan accordingly
-
Ignore the change as it is external and focus on the original plan
-
Request additional funding to incorporate the new technology without assessing its impact
-
Outsource the technological components to a third party to mitigate risk
Correct answer: Conduct a risk assessment to understand the impact and then update the project plan accordingly
Project alterations often stem from the need to manage new risks, which may arise internally from team actions or externally from factors beyond the team's control. In response, project managers and their teams must craft and implement solutions to reestablish project stability.
Ignoring significant external changes can lead to project failure or obsolescence. It's essential to assess and adapt to external changes.
Requesting additional funding without first assessing the impact of the new technology can lead to inefficient use of resources and may not address the underlying risk.
Outsourcing without first understanding the risks and impact of the new technology might not be the most effective solution and could introduce new risks.
84.
A risk manager is working with her team to evaluate risks. She identifies various unknown-unknowns. Which of the following best describes unknown-unknowns as a risk classification?
-
They are emergent risks that are essentially unknowable in the context of portfolio, program, and project management
-
They are well-known risks that are easily manageable in the context of portfolio, program, and project management
-
They are predetermined risks that are entirely predictable in the context of portfolio, program, and project management
-
They are transparent risks that pose no challenges in the context of portfolio, program, and project management
Correct answer: They are emergent risks essentially unknowable in the context of portfolio, program, and project management
Unknown-unknowns are emergent risks essentially unknowable in the context of portfolio, program, and project management. Managing these risks involves organizational resilience, including research, awareness-raising, challenging the status quo, and promoting information flow, preparing organizations to respond and recover from unforeseeable events.
Unknown-unknowns, by definition, are not well known or predictable. They are not predetermined.
Unknown-unknowns are characterized by their lack of transparency and their potential to present significant challenges precisely because they are not initially recognized or understood.
85.
Your project is well underway, and you've just received feedback from a key stakeholder indicating potential scope omissions. The stakeholder points out that some critical requirements might have been missed during the initial project planning phase. What is your immediate action?
-
Convene a meeting with the project team to analyze the feedback and assess its impact on the project
-
Dismiss the stakeholder's concerns, as the project plan is already in motion
-
Document the feedback but take no further action
-
Initiate a scope change request without further investigation
Correct answer: Convene a meeting with the project team to analyze the feedback and assess its impact on the project
Scope omissions are a common challenge in project management, arising when the project team inadvertently overlooks or fails to incorporate crucial elements of scope that are essential to meeting project objectives. This oversight can stem from a variety of factors, such as miscommunication between stakeholders, incomplete requirements gathering, or a lack of thorough analysis during project initiation.
Dismissing valid stakeholder concerns can lead to project issues.
Simply documenting feedback without analysis may not address potential scope omissions.
Initiating a scope change request without a thorough investigation can be premature.
86.
A manufacturing company sources materials from various international vendors. With geopolitical tensions on the rise in one of the source countries, the supply chain manager is considering their options. What action should the supply chain manager take based on risk attitudes?
-
Assess the potential risks of supply disruption, explore alternative sourcing options, and maintain open communication with the current vendors to monitor the situation
-
Immediately terminate all contracts with vendors from the country
-
Assume that geopolitical tensions will not affect their specific shipments
-
Continue the contracts but prepare a public statement denying any association with the country's politics
Correct answer: Assess the potential risks of supply disruption, explore alternative sourcing options, and maintain open communication with the current vendors to monitor the situation
Risk attitude represents a disposition towards uncertainty that is consciously or subconsciously adopted by individuals and groups, influenced by perception, and manifested through observable behavior. It reflects an organization's approach to assessing and, if warranted, pursuing, retaining, embracing, or avoiding risk. Risk attitudes can span the spectrum from risk aversion to risk-seeking behavior.
Immediate termination without proper risk assessment is extreme and might be unnecessarily risk-averse.
Ignoring potential risks is a manifestation of risk neglect rather than a balanced risk attitude.
Public statements don't address the core supply chain issue.
87.
Aimee, the CEO of TechFlow Inc., is considering expanding the company's operations into a new market. Before making a decision, she wants to ensure that all potential risks are identified. Which of the following should she prioritize?
-
Engaging in a comprehensive risk identification process to uncover potential threats and opportunities
-
Conducting market analysis to determine profitability
-
Reviewing past financial statements to forecast future revenue
-
Hiring a new marketing team to promote the expansion
Correct answer: Engaging in a comprehensive risk identification process to uncover potential threats and opportunities
Risk management is an ongoing process that doesn't conclude. As the business environment evolves and new strategic opportunities arise, organizations must review their risks, identify new ones, and adapt to changing circumstances. This dynamic process may also necessitate building greater organizational capabilities.
While market analysis is essential, it primarily focuses on profitability and not risk identification.
Past financial statements can provide insights into the company's performance but do not identify potential risks in a new market.
Hiring a marketing team is a tactical move and does not directly address risk identification.
88.
You are leading a risk analysis for your organization and are reviewing various risk characteristics. Which of the following best defines strategic impact in the context of risk management?
-
A high strategic impact suggests that the risk has the capacity to significantly affect the organization's strategic direction
-
A high strategic impact suggests that the risk has a minor capacity to affect the organization's strategic direction
-
A low strategic impact suggests that the risk has the capacity to significantly affect the organization's strategic direction
-
A high strategic impact suggests that the risk has no capacity to affect the organization's strategic direction
Correct answer: A high strategic impact suggests that the risk has the capacity to significantly affect the organization's strategic direction
Strategic impact gauges the potential effect of a risk, whether positive or negative, on an organization's strategic goals and objectives. A high strategic impact suggests that the risk may significantly affect the organization's strategic direction.
Low strategic impact implies that the risk has a limited capacity to affect the organization's strategic direction.
89.
A project team is monitoring key performance indicators (KPIs) and notices a consistent deviation from the planned metrics in project deliverables. What should be the immediate action taken by the project manager?
-
Investigate the cause of the deviations and take corrective action
-
Ignore the deviations as minor and focus on major deliverables
-
Postpone addressing the deviations until the next project phase
-
Increase the project budget to accommodate potential delays
Correct answer: Investigate the cause of the deviations and take corrective action
Early detection of potential issues through key performance indicators is invaluable for project management. Early awareness allows for prompt action, often resulting in reduced change costs and better project outcomes.
Ignoring deviations, even if minor, can lead to larger issues later in the project.
Postponing the response to deviations can exacerbate the problem and increase the cost and effort required for corrections.
Increasing the budget does not address the root cause of the deviations and can lead to inefficient resource utilization.
90.
Richard, the head of compliance in a financial institution, is in the process of developing a comprehensive plan that outlines how risk management processes will be integrated with regulatory compliance efforts. Which term accurately represents this plan?
-
Risk management life cycle
-
Risk loop
-
Risk threshold
-
Risk aversion
Correct answer: Risk management life cycle
The risk management life cycle is a structured method for comprehensively addressing risks across the enterprise, portfolio, program, and project domains. While the specific practices for managing risks may vary among these domains and organizations, an overarching life cycle approach outlines a logical sequence of phases. These phases can be repeated as needed and typically include processes such as planning risk management, identifying risks, performing qualitative and quantitative risk analysis, planning and implementing risk responses, and monitoring risks.
Risk loop is not a standard term in risk management.
Risk threshold is the measure of acceptable variation in an objective.
Risk aversion is a reluctance to take on risk.
91.
You are a risk management professional working on a project. During a risk identification meeting, a team member suggests the assumption that "the project will be completed within the allocated budget and schedule" is a project risk. What should you do?
-
Explain the difference between assumptions and risks and categorize it as an assumption
-
Agree with the team member and add it to the risk register
-
Disagree with the team member and explain that it is a valid project assumption
-
Suggest conducting a risk analysis to determine whether it should be classified as a risk
Correct answer: Explain the difference between assumptions and risks and categorize it as an assumption
It is essential to differentiate between valid project assumptions and actual project risks in the context of project planning and execution. Project assumptions typically represent conditions that establish the project's connection to known constraints. For example, they might involve restricting certain activities to enable future project reevaluation, thereby minimizing the performance risk of staying within a specific budget and schedule.
Adding it to the risk register as a risk is not the correct approach because this statement is actually a project assumption.
Disagreeing with the team member and explaining that it's a valid project assumption is the correct course of action.
While it's good to consider the statement, conducting a risk analysis would confirm its status as an assumption, so this step is not necessary.
92.
Halfway through a project's timeline, the project manager notices that the team's performance is not aligning with the planned objectives. What should be the project manager's immediate course of action?
-
Conduct a variance analysis to identify the root causes and implement corrective actions
-
Extend the project's deadline without any analysis
-
Reduce the project's scope to match the team's performance
-
Reassign team members based on their performance
Correct answer: Conduct a variance analysis to identify the root causes and implement corrective actions
Project plans balance multiple constraints: scope, cost, schedule, resources, quality/technical performance, and overall risk. Alterations in any one of these areas are likely to affect others, highlighting the interconnected nature of project management.
Simply extending the deadline without understanding the reasons for the misalignment might not address the underlying issues.
Reducing the scope might not be the best solution, especially if the performance issues can be addressed.
Reassigning team members without a thorough analysis might not solve the performance issues and could lead to further disruptions.
93.
You're the risk management leader for a financial institution. During a risk strategy meeting, a team member proposes taking on a risk that is relatively simple to assess and measure but offers minimal rewards. What should you highlight regarding this proposal?
-
Emphasize the importance of assessing risks effectively
-
Accept the risk immediately due to its simplicity
-
Reject the risk as it doesn't promise significant rewards
-
Seek external expertise to handle the risk assessment
Correct answer: Emphasize the importance of assessing risks effectively
An organization should only embark on risks that it can assess, measure, manage, monitor, and report effectively. In conjunction with risk identification, these components constitute the steps and actions involved in the risk process.
Accepting a risk solely based on its simplicity is not prudent without considering the rewards.
Rejecting a risk solely based on potential rewards might overlook other factors.
Seeking external expertise doesn't directly address the importance of assessing risks effectively.
94.
Which term relates to the time frame before a risk is expected to impact objectives?
-
Proximity
-
Risk imminence
-
Objective time frame
-
Preparation window
Correct answer: Proximity
Proximity indicates the time frame within which a risk is likely to have an impact on one or more objectives. A short proximity suggests that the risk's potential impact is imminent, underscoring the urgency of preparing for its effects.
Risk imminence is not a standard term used in risk management. While it conveys the concept of a risk being imminent, it is not a recognized term in formal risk management frameworks.
Objective time frame does not specifically refer to the time before a risk is expected to impact objectives. The term proximity is more specific for indicating this concept.
Preparation window implies a time frame for preparing for a risk but does not specifically denote the period before a risk is expected to impact objectives.
95.
As a senior manager for your organization, you are investigating an incident that took seven days to resolve, and you begin using an analysis technique. What type of analysis investigates the common underlying causes of interconnected risks and seeks to identify additional related risks, with the goal of developing preemptive and comprehensive responses to simplify risk management complexity?
-
Root-cause analysis
-
Situational analysis
-
Problem analysis
-
Risk analysis
Correct answer: Root-cause analysis
Root-cause analysis is a valuable process for uncovering interconnected risks that may share underlying causes. By delving into the root causes, we can identify additional, related risks. This analysis forms the foundation for crafting proactive and thorough risk mitigation strategies, ultimately simplifying the apparent complexity of risk management.
Situational analysis typically focuses on examining the current circumstances or conditions in a specific context.
Problem analysis generally involves identifying and analyzing issues or challenges. While it may be related to risk management, it does not specifically address the identification of interconnected risks and their underlying causes.
Risk analysis is a broader term that encompasses various methods of assessing and evaluating risks.
96.
You are a project manager leading a complex software development project. During a risk identification meeting, one of your team members suggests that identifying project risks is unnecessary because you have a well-experienced team. What is the most appropriate response to this suggestion?
-
Explain that risk identification is essential regardless of team experience and continue the process
-
Acknowledge the team member's experience and skip risk identification
-
Agree with the team member and proceed to risk mitigation
-
Politely thank the team member for their input and continue with risk identification
Correct answer: Explain that risk identification is essential regardless of team experience and continue the process
Inadequate identification, assessment, management, and control of project risks can result in unforeseen issues that undermine the project's success. Insufficient planning and management of risk reserves can also negatively impact the project.
Acknowledging the team member's experience and skipping risk identification are not best practices.
Agreeing with the team member without assessing risks can lead to unforeseen issues.
Ignoring risk identification based on team experience is not recommended.
97.
In a marketing team, Emma, a junior member, made a significant decision regarding a high-profile advertising campaign without consulting her supervisor. The decision led to both positive outcomes (increasing customer engagement) and negative consequences (breaching the budget). Although Emma's role didn't grant her the authority to make such decisions, she took the initiative. Which term best describes the situation in which Emma might be held responsible for her actions?
-
Accountability
-
Responsibility
-
Authority
-
Probability and impact
Correct answer: Accountability
Accountability is inherently individual and arises from one's role within the organization. It is closely tied to one's authority, usually aligning with the limits of the authority granted. However, in some instances, individuals may be held accountable for actions or decisions that extend beyond their authorized scope.
Responsibility focuses on willingness to assume specific tasks or functions. While Emma did take on a significant task, the question is more about her being answerable for the consequences.
Authority is the power or right to make decisions within predefined boundaries. Emma did not have the authority to make the decision in question.
Probability is the likelihood that a risk will occur, and impact is the potential consequences of a risk.
98.
Samantha, the Chief Risk Officer at PB Enterprises, is tasked with assessing the risks of entering a new market. The market dynamics are largely unknown, and limited data are available. How should Samantha proceed to ensure a comprehensive risk assessment?
-
Utilize a mix of quantitative data and qualitative analysis, including expert opinions and market analysis
-
Focus only on the financial aspects since they are the most critical in new market entries
-
Depend entirely on industry benchmarks and competitor analysis for risk assessment
-
Conduct a risk assessment based only on the available data, ignoring market uncertainties
Correct answer: Utilize a mix of quantitative data and qualitative analysis, including expert opinions and market analysis
Risk assessment and measurement aim to foster a deep understanding of risk exposures, including their magnitude, sources, direction, and key drivers. Some risks can be quantified, while others can only be assessed qualitatively, relying on experience and analytical and intuitive thinking.
Focusing only on financial aspects neglects other potential risks like cultural, regulatory, and operational risks in a new market.
Relying solely on industry benchmarks and competitor analysis may not capture the unique challenges and opportunities of the new market.
Conducting an assessment based only on available data can miss understanding the broader, uncertain aspects of the new market.
99.
You are managing a project with a significant external dependency. Despite your best efforts, the estimated budget and time for implementing fallback plans or residual risk responses are inadequate. What should be your next step?
-
Evaluate trade-off options and make necessary adjustments to address the inadequacies
-
Proceed with the original project plan and hope for the best
-
Inform stakeholders about the budget and time constraints but continue without changes
-
Discontinue the project to prevent any further risk exposure
Correct answer: Evaluate trade-off options and make necessary adjustments to address the inadequacies
Some project scope may depend on external events. If the estimated budget and time for implementing fallback plans or residual risk responses prove insufficient, the project team must evaluate trade-off options, potentially jeopardizing major project objectives.
Proceeding without addressing the inadequacies would likely result in project failure.
Merely informing stakeholders without taking corrective action is insufficient.
Discontinuing the project should only be considered as a last resort in extreme circumstances.
100.
A project manager is preparing to create a project scope statement for a construction project. What aspect of the project scope statement is most likely to introduce risks?
-
The specifications and delivery methods for project outcomes.
-
The project's location and site conditions.
-
The project's communication plan and stakeholder analysis.
-
The project manager's qualifications and experience.
Correct answer: The specifications and delivery methods for project outcomes.
Project scope statements introduce several risks, predominantly associated with the specifications and delivery methods for products, services, or other expected outcomes within the project's defined scope.
While relevant or important aspects to the project, each of these is not typically part of the scope statement that introduces risks:
- The project's location and site conditions
- The communication plan and stakeholder analysis
- The project manager's qualifications and experience